Portland Golf Club – established in 1914 and host to numerous major championships and the 1947 Ryder Cup – has completed the first phase of renovation to its historic golf course. Led by architect Dan Hixson, an Oregon native who’s lived in Portland for 35 years, the project evolved incrementally over the past decade and targeted playing areas on all 18 holes.
The project began about 10 years ago with the removal of approximately 75 trees throughout the course, including more than 20 around the 13th green, opening it to more sunlight and air flow. Hixson continued overseeing a tree-maintenance program while submitting a master plan for overall course improvements. Work started eight months ago and was completed this month.
“Out of respect to our rich golf history, the board wanted to preserve the integrity of our golf course, while improving it for the modern game,” said John Vranizan, President, Board of Directors, Portland Golf Club. “Our focus is to enhance the member experience, striving to be better from the moment a member sets foot on the golf course.
“Working closely with Dan, the construction, and agronomy teams, we meticulously upgraded every hole on the golf course.”
The scope of work included:
Bunkers. The plan’s main focus was the bunkering, improving drainage while making them both more strategic and attractive. There are now 51 bunkers where there had been 63, while another 15 were repositioned to affect play (positioned in doglegs and at proper distances). Each bunker on the course has been rebuilt with Better Billy Bunker II system and filled with new, brighter sand (S900) for contrast.
Hixson cited bunker shaper Tony Russell as having a great impact on the contouring and visual appeal of these hazards.
“There is a homogenized style with greatly enhanced aesthetic appeal due to improved drainage and sand quality. The bunker style is unique to Portland Golf Club based on capturing and retaining the best existing characteristics and topographical features,” he said.
Greens. Nearly every green was enlarged to maintain their original character while adding flagstick positions. Greens were expanded at holes 1, 3, 4, 5, 6, 7, 9, 10, 12, 17, and 18, while the 15th green was totally rebuilt.
“Facing many clubs of this era are the tremendous changes in green speeds,’’ Hixson said. “Plus, there are some very steep greens here and we didn’t want to tear into them unless it was absolutely necessary. On many, we expanded at the corners, often in conjunction with the bunker work we were doing. We’ve even gotten down on the ground and used our hands to get the new turf to lay perfectly so it looked like it’s always been there. We like to say this course was ‘hand-made.’”
Tees. Nearly a dozen holes saw tee boxes re-graded and re-grassed to make them more uniform. Plus, new forward tees were added to holes 1, 3, 5, 7, 8, 9, 10, 14, 16, and 18 to make the course enjoyable for more players, especially those with slower swing speeds. The forward tees play to approximately 4,800 yards, aligning the distance with the USGA’s Tee It Forward initiative, according to Vranizan.
While most of the changes were detailed in Hixson’s master plan, he said the club allowed him to be flexible since.
“The best designs happen in the field. This allows me to be more creative and it’s more efficient without wasting money. The club gave me a great deal of freedom, making for an awesome project. I love work of this nature and the results are showing.”
An irrigation infrastructure project, including the installation of all new heads, is scheduled to start in spring 2023 and take approximately six months. Brent Harvey, an international irrigation specialist, will oversee the installation.
Portland Golf Club is in discussions to host future Oregon Golf Association and USGA championships on the renovated layout, which now stretches to 7,100 yards.
Photo Courtesy of Portland Golf Club